Office Fitout Budget Template for Melbourne Projects
The biggest risk in an office fitout budget isn’t always the total. It’s what each proposal leaves out. An office fitout budget template that breaks the project into packages makes design, trades, services and finishes visible before you compare estimates.
This template gives you the package headings, the tracking fields and a way to compare proposals on scope, not just price. Copy the tables into Excel or Google Sheets and adapt them to your project.
How to Use This Template
- List your packages. Use the headings below and delete any that don’t apply.
- Fill in scope first, figures later. Record inclusions and exclusions before any dollar amount. Leave financial fields blank until you have project-specific figures.
- Keep three amounts apart. Estimates, approved commitments and actuals each get their own column, so a forecast never gets mistaken for a commitment.
This is a planning tool, not a quote. For benchmark costs, see our commercial fit-out costs guide.
Part 1: Package Headings
| Package | What it covers | Required, optional or undecided |
|---|---|---|
| Design and approvals | Plans, design coordination, permit-related items | |
| Strip-out and site works | Removal of existing fit-out, if applicable | |
| Electrical and data | Power, lighting circuits, data and communications | |
| Hydraulic and mechanical | Plumbing, air conditioning and ventilation | |
| Partitions and glazing | Internal walls, glazed screens, doors | |
| Ceilings and lighting | Suspended ceilings, light fittings | |
| Flooring | Carpet, vinyl, tiles or other finishes | |
| Painting and finishes | Painting, joinery, feature finishes | |
| Furniture and equipment | Listed separately if part of the brief | |
| Relocation | Moving staff, furniture and equipment | |
| Provisional allowances | Items not yet specified or decided |
Part 2: Fields for Every Package
| Field | What to record |
|---|---|
| Inclusions | What the line covers and where responsibility starts and ends |
| Exclusions | Work the line leaves out |
| Decision-maker | Who confirms the scope or approves a change |
| Estimate | Planning figure, with its basis |
| Commitment | Approved amount |
| Actual | Amount paid or invoiced |
| GST basis | Whether the figure is ex GST or inc GST |
| Variance and status | Difference from the approved position, labelled provisional, approved or committed |
| Assumptions | Dependencies and decisions that could change the allowance |
| Source and date | The proposal, drawing or scope document behind the entry, and when it was last updated |
Example row (figures left blank):
| Package | Inclusions | Exclusions | Decision-maker | Estimate | Commitment | Actual | GST | Status | Assumptions | Source and date |
|---|---|---|---|---|---|---|---|---|---|---|
| Electrical and data | New power and data points to the approved layout | Switchboard upgrade | Facilities manager | Ex GST | Provisional | Existing cabling is reused | Electrical proposal, rev B, 12 Oct |
Compare Proposals by Package, Not by Total
Put each proposal against the same package headings. For every line, record what’s included, what’s excluded, the assumptions and any unresolved decision. A headline total can hide scope differences that this shows.
Watch the places where work falls between packages:
- Service interfaces: where does one trade’s work end and the next begin?
- Approvals: who prepares, coordinates or obtains each project-specific approval?
- Provisional allowances: keep them apart from confirmed scope, and note what decision resolves each one.
After you choose a proposal, keep using the same register. Update each package when its scope is approved or changed. For businesses managing a fitout as part of broader commercial growth or entering new markets abroad, investing in digital reach through SEO services UAE can ensure your online presence expands alongside your physical footprint.
Track Changes Without Losing the History
Add a change log alongside the register:
| Date | Change | Package affected | Reason | Approved by | Budget impact | Supporting document |
|---|
Keep the earlier approved entry and add a dated revision, so you can tell agreed scope from a later proposal.
Turn the Register Into a Delivery Brief
A completed register shows what will be delivered, where each package starts and ends, and which decisions are still open. Bring design, permits, trades and services into one brief, and record who is accountable for each interface.
A1 Precision Solutions delivers turnkey commercial office projects with a single point of contact across design, permits, construction, utilities and final fit-out. Start with office fit-outs and our design, plans and permits service. For how a managed project runs from phase to phase, see our office fit-out project management guide. If staff and equipment are moving too, see business relocations.
Contact A1 Precision Solutions to discuss your Melbourne office project.
Frequently Asked Questions
Should the template show figures with or without GST?
Either works if you label it and apply it consistently. Use the GST basis column so every estimate, commitment and actual follows the same treatment. A1 quotes ex GST, with GST charged on all lines including permits, so record A1 figures as ex GST.
When should I prepare the budget?
While you’re still defining what the project must deliver, before scope decisions are settled. Mark early entries as planning estimates with their assumptions, and update them as design, approvals and proposals develop. Our planning checklist covers what to decide first.
Can one template cover a staged project?
Yes. Add a stage column to each package. Assign shared items, such as design coordination, to one stage or a central package so they aren’t counted twice.
How do I plan a fit-out while staff stay on site?
Record operating constraints separately from construction scope, for example a meeting space that must stay available. Add disruption controls to the agreed scope once they’re defined, instead of assuming they’re included.
Disclaimer
Information in this article is general in nature. For advice specific to your facility, contact A1 Precision. See our full Disclaimer and Privacy Policy.