The contract, not a universal Victorian rule, sets the defects liability period (DLP) for an office fitout. Commercial construction contracts commonly provide 12 months, but the agreed terms decide the period, what it covers and how you must report a defect.

A DLP is the agreed time after practical completion when the builder must rectify covered defects in workmanship or materials. It is not a product warranty, and when it expires it doesn’t automatically settle every question about your rights.

This guide explains who is responsible for repairs, what to do when you find a defect, how a DLP differs from a product warranty, and what to define in the contract before work starts.

Key Takeaways

  • Check the contract for the DLP length, the work it covers and how you must give notice.
  • Record defects and notify the contractor in writing so the agreed rectification process can begin.
  • Give the contractor a reasonable opportunity to inspect and repair covered defects before arranging other work.
  • Keep the contract’s rectification process and product warranties separate. Each has its own terms and scope.

Who Is Responsible for Fixing Defects?

The builder named in the contract is responsible to the owner for rectifying covered defects, even when a subcontractor carries out the repair. Faulty workmanship, or materials that don’t meet the contract requirements, generally fall within the process.

A builder is generally not responsible for damage caused by misuse, fair wear and tear, or events outside its control. A stain from a leaking installation and a stain from a spill after occupation can involve different responsibilities, so the cause matters. Record when an issue appeared and any relevant changes or incidents.

When does the period start?

The DLP generally runs from practical completion, the stage the contract uses to assess whether the work is sufficiently complete for handover. A staged project may define practical completion separately for each section, so check the start date for the area affected.

What to Do When You Find a Defect

  1. Notify the builder in writing. Describe the location, the impact and the visible signs.
  2. Keep records. Dated photographs, correspondence and inspection records give a clear history.
  3. Allow inspection and access. Give the contractor a reasonable opportunity to assess and arrange rectification under the contract.
  4. Limit further damage. If urgent action is needed to protect people or property, record the condition first, why the work couldn’t wait and what was done. Separate temporary protection from permanent rectification, and keep removed materials where practical.
  5. Close the item in writing. Require sign-off against the agreed scope rather than treating a site visit as proof the repair is complete.

Keep one defect register linked to the room, drawing or asset. Log a damaged partition separately from a door that fails to latch, and record who received notice, the inspection findings and the repair completion date.

DLP vs Product Warranty

A DLP covers defects in the contracted work. A product warranty covers a named item or component, such as equipment a manufacturer supplies. A manufacturer may cover a component failure while installation quality is assessed under the construction contract.

At handover, match warranty documents and manuals to the installed assets, and record model details, supplier information and commissioning records. Our office refurbishment checklist covers the handover pack and snag list. If a fault develops, read both the warranty and the contract’s rectification clause before arranging replacement work, because one may require a manufacturer assessment while the other sets a separate notice process.

Contract expiry doesn’t automatically end every other right. For anything beyond the contract’s own process, get legal advice on your situation.

What to Define in the Contract

The DLP clause should state:

  • the covered work, and when the period starts and ends
  • how notices are served and who can inspect
  • how access is arranged and how repairs are accepted
  • how disputed causes and incomplete repairs are handled
  • any extension where a defect is rectified late in the period
  • subcontractor terms that line up with the head contract, so a trade’s repair window doesn’t end before the contractor’s responsibility does

Setting Up Your Next Fitout With A1 Precision Solutions

Clear scope and handover records make defect management easier, because they separate agreed work from later changes. A1 Precision Solutions delivers office fit-outs in Melbourne under a turnkey model, covering planning, coordination and handover. Our office fit-out project management guide explains how final walkthroughs and defect lists fit into delivery.

When you compare builders, ask how each one handles changes and closes out outstanding items. Our checklist on how to compare commercial fitout quotes covers it. To discuss your scope and handover requirements, contact A1 Precision Solutions.

Frequently Asked Questions

How long is an office fitout defects liability period?

The contract sets it. Commercial contracts commonly provide 12 months, but there’s no single period for every project. Check the start date, the covered work and the notice requirements.

How should DLP rectifications be tracked?

Keep one defect register linked to the relevant room, drawing or asset. Record when each fault appeared, who received notice, the inspection findings, agreed actions and the repair date, and attach dated photographs and correspondence.

What are a builder’s obligations during the DLP?

The builder must meet the rectification obligations in the contract for covered faults. The process may require an inspection, access to the affected area and repair work. The builder can assess whether the condition relates to workmanship, materials, later damage or maintenance.

What happens if defects aren’t resolved?

Follow the contract’s dispute process and keep notices, responses and inspection records together. Document the outstanding issue and the resolution you want before escalating, and get legal advice on your options.

Who is responsible during the DLP, the contractor or the subcontractor?

The head contractor is generally responsible to the client for the contracted work, while the relevant subcontractor may carry out the repair. Use the notification route in the head contract, and record the responsible trade and the head contractor’s response.

Disclaimer

Information in this article is general in nature. For advice specific to your facility, contact A1 Precision. See our full Disclaimer and Privacy Policy.