Project Description

Client:   Not disclosed
Location:   Melbourne
Surface Area:  
Year Completed:   2021
Raised Storage Area designed and built high to allow for machinery below.

The Challenges

Project: Mezzanine raised storage floor.

Client Brief:

The client required an enclosed room to house new machinery but didn’t want to lose storage area in the facility. This meant a storage area would need to be created above the new room being built. This was an ideal situation for a mezzanine or raised storage area, allowing more room of the facility to be used effectively.

Scope of Works:

  • Initial site inspection and consultation;
  • Design and engineering of an enclosure incorporating a mezzanine raised storage area above to meet the client’s requirements for load rating, clear span spacing underneath, pallet loading, forklift access, etc…;
  • Fabrication of custom heavy-duty stairs with steel treads;
  • Fabrication and installation of the mezzanine raised storage area and stairs;
  • Installation of the hand rail and sliding gate.

Outcomes:

All works were carried out whilst the business was still operational, with minimal disruption to the business, on time, on brief, and on budget.